The Largest U.S. Grid Operator Puts 1,200 Mostly Solar Projects on Hold for Two Years
View
Date:2025-04-13 21:57:14
The nation’s largest electrical grid operator has approved a new process for adding power plants to the sprawling transmission system it manages, including a two-year pause on reviewing and potentially approving some 1,200 projects, mostly solar power, that are part of a controversial backlog.
PJM Interconnection operates a competitive market for wholesale electricity in all or part of 13 states and the District of Columbia, from Virginia to northern Illinois. Its plan is the result of work over the past year by PJM and what it calls its stakeholders, according to a press release from PJM. They include electric utilities, electric transmission owners, state and consumer interests, and solar and wind developers.
“These changes represent a landmark accomplishment for PJM stakeholders and staff that establishes a better process to handle the unprecedented influx of generation interconnection requests and is critical to clearing the backlog of projects,” said PJM President and CEO Manu Asthana.
PJM remains committed to a strategy of “decarbonization policies while preserving reliability and cost-effectiveness,” Asthana said.
But the backlog, and a two-year pause on so many projects with the potential for even longer delays on new proposals, has frustrated a number of renewable energy developers.
In January, an outspoken Adam Edelen, a former Kentucky state auditor who runs a company working to bring solar projects and jobs to ailing coal communities in Appalachia, said he was concerned that “the kink in the system” was helping to delay effective climate policy in the United States. “The planet does not have time for a delay,” he said at the time.
Approval delays were putting solar developers in a financial bind and calling into question the Biden administration’s goal of having a carbon-free electricity grid in just 13 years, he cautioned.
Edelen late Thursday afternoon said he was still reviewing PJM’s announcement, which went out on Thursday.
“The current situation is preventing clean energy projects from coming online and is unsustainable,” said Kat Burnham, a principal of Advanced Energy Economy, a trade group for clean energy businesses that has expressed frustration with the situation. “While the reforms aren’t perfect, the updated process will help mitigate the project backlog. Any further delays would be worse for advanced energy projects and America’s clean energy transition.”
A PJM spokesman, Jeffrey Shields, said PJM would send its plan to the Federal Energy Regulatory Commission in May. FERC has 60 days to act on the plan, or it could not act and the plan would go into effect, Shields said.
Over the last four years, PJM officials have said they have experienced a fundamental shift in the number and type of energy projects seeking to be added to a grid, each needing careful study to ensure reliability. It used to be that PJM would see fewer, but larger, fossil fuel proposals. Now, they are seeing a larger number of smaller, largely renewable energy projects.
In all, there are about 2,500 projects awaiting action by the grid operator, which is based in Valley Forge, Pennsylvania, outside Philadelphia.
PJM has put forward a two-phased solution.
A new approval process will put projects that are the readiest for construction at the front of the line, and discourage those that might be more speculative or that have not secured all their financing.
Then, an interim period will put a two-year delay on about 1,250 projects in their queue—close to half of the total—and defer the review of new projects until the fourth quarter of 2025, with final decisions on those coming as late as the end of 2027.
Shields said that during the two-year transition, PJM will continue to work on more than 1,200 projects, which include more than 100,000 megawatts of renewable energy. “There is no shortage of renewables poised to come online,” he said.
The backlog, caused in part by the explosion of interest in solar energy, varies by state. Earlier this year, there were hundreds of projects waiting for review in states like Pennsylvania and Virginia, and dozens in states like Kentucky and West Virginia.
The Pennsylvania Energy Office was still reviewing the plan, said its spokesman, Jamar Thrasher, on Thursday.
“We support the changes PJM is implementing to create a more efficient and effective process, which will allow for the timely interconnection of generation to the PJM grid while ensuring reliability,” said Tammy Ridout, spokeswoman for the Ohio-based utility AEP.
“These improvements are critical to handle the influx of interconnection requests we have seen in recent years and will see for the foreseeable future,” said Ken Seiler, PJM vice president of planning, in a written statement. “This plan represents a real compromise among many different interests to get renewable and other projects through the queue as fast as possible and give developers a clearer picture of their costs and timelines.”
veryGood! (12)
Related
- Hackers hit Rhode Island benefits system in major cyberattack. Personal data could be released soon
- Humpback Chub ‘Alien Abductions’ Help Frame the Future of the Colorado River
- United Airlines CEO blasts FAA call to cancel and delay flights because of bad weather
- Coal’s Decline Not Hurting Power Grid Reliability, Study Says
- Israel lets Palestinians go back to northern Gaza for first time in over a year as cease
- With Biden’s Win, Climate Activists See New Potential But Say They’ll ‘Push Where We Need to Push’
- American Climate Video: An Ode to Paradise Lost in California’s Most Destructive Wildfire
- Biden promises internet for all by 2030
- Paula Abdul settles lawsuit with former 'So You Think You Can Dance' co
- Vanderpump Rules Tease: Tom Sandoval Must Pick a Side in Raquel Leviss & Scheana Shay's Feud
Ranking
- How to watch new prequel series 'Dexter: Original Sin': Premiere date, cast, streaming
- Small businesses got more than $200 billion in potentially fraudulent COVID loans, report finds
- Coal’s Decline Not Hurting Power Grid Reliability, Study Says
- American Climate Video: A Pastor Taught His Church to See a Blessing in the Devastation of Hurricane Michael
- Sonya Massey's father decries possible release of former deputy charged with her death
- New York, Massachusetts Move on Energy Storage Targets
- Chicago has the worst air quality in the world due to Canadian wildfire smoke
- Four men arrested in 2022 Texas smuggling deaths of 53 migrants
Recommendation
Taylor Swift Eras Archive site launches on singer's 35th birthday. What is it?
Kim Kardashian Recalls Telling Pete Davidson What You’re Getting Yourself Into During Romance
Supreme Court rejects independent state legislature theory in major election law case
Ryan Seacrest named new Wheel of Fortune host
Military service academies see drop in reported sexual assaults after alarming surge
Navajo Nation Approves First Tribal ‘Green Jobs’ Legislation
Ali Wong Addresses Weird Interest in Her Private Life Amid Bill Hader Relationship
Man charged with murder in stabbings of 3 elderly people in Boston-area home